Published lifecycle milestones​

The Microsoft migration overview describes BizTalk Server 2020 as the final release and publishes the following dates. Reviewed 3 November 2026.

MilestoneDateMeaning
Expected end of sales31 March 2027A sales milestone, not an immediate shutdown or end of support
Mainstream support milestone12 April 2028Plan assessment, implementation and cutover with contingency
Planned optional paid extended-mainstream support begins13 April 2028Eligible customers only, subject to final terms and coverage
Expected end of that optional offering10 April 2030Temporary migration coverage, not a guaranteed extension for every customer
Confirm the applicable agreement

The optional paid offering remains subject to eligibility, exclusions, coverage, pricing and purchasing terms. BAM, ESB Toolkit, industry accelerators and some legacy dependencies are specifically called out for early assessment in the overview. A paid agreement does not remove the need to migrate or redesign excluded features.

The Lifecycle listing displays mainstream and extended dates in Pacific Time and contains a note with a different mainstream date presentation. The overview and listing also use different extended-support terminology. Confirm the exact applicable date and entitlement with Microsoft rather than resolving commercial terms from this hub.

These milestones apply to the named product lifecycle. They do not restrict which source estate you can assess with the Agent.

Primary announcements​

Use a representative implementation to expose technical unknowns before committing to a broad schedule. Lifecycle policies and support agreements are separate considerations from the engineering guidance in this hub.

Start with discovery, not a deadline assumption​

Inspect shared dependencies, custom behavior and remediation work early. Use measured implementation and test effort rather than committing a schedule from artifact counts alone.

Keep commercial decisions separate

Confirm lifecycle policies, support agreements and any optional support offering directly with Microsoft. They are planning constraints, not Agent eligibility checks or guarantees of migration duration.

These are recommended delivery phases, not Microsoft-mandated deadlines or promised durations. Work backwards from your organization's approved completion date with contingency.

Now: assess and fund​

  • Identify interface owners and the scope of the existing implementation.
  • Baseline message flows, operational costs, custom code and specialist dependencies.
  • Inspect dependencies and identify high-risk redesign items.
  • Obtain sponsorship, capacity, budget and engagement routes.

Exit: a reviewed inventory, risk register, initial target architecture and funded pilot.

Next: prove patterns and migrate priority waves​

  • Complete a representative implementation before scaling migration.
  • Approve hosting, network connectivity, identity, HA/DR and cost.
  • Sequence dependencies and establish reusable patterns and tests.
  • Move high-risk unknowns into early engineering spikes, not the last release.

Exit: repeatable implementation patterns and accepted migration waves.

Before your approved completion date: cut over​

  • Rehearse freeze, drain, reconciliation, routing switch and rollback.
  • Pass functional, performance, security and operations acceptance.
  • Reserve business-owner availability for release decisions and hypercare.

Exit: signed acceptance, reconciled messages and stable target operations.

After stabilization: decommission​

  • Confirm retention and audit obligations.
  • Remove remaining dependencies, secrets and routing only after approval.
  • Archive source, configuration, migration decisions and acceptance evidence.
  • Retire licenses and infrastructure through your normal change process.

Exit: a signed retirement record.